Main Article Content

Abstract

The research is to analysis the effect of reducing manpower for production process railroad bridge WTT46.5 type. The purposed manpower reduction is to increased effective production process railroad bridge WTT46.5 type and reduction manpower cost. Reduction of Manpower happened in trial process with the number 15 people and separated in some part. On of the part is in welder that is reduction in one person. Manpower reduction in trial process to improve company finance by Rp.  4.645.620,00 in every project.

Keywords

manpower railroad bridge trial process

Article Details

References

  1. Fatkhurrohman, Arief, ”Penerapan Kaizen Dalam Meningkatkan Efisiensi Dan Kualitas Produk Pada Bagian Banbury PT Bridgestone Tire Indonesia”,Jurnal Administrasi Kantor, Bekasi Timur, 2016.