The process of housing development is inseparable from labor productivity. This study aimed to determine the value of LUR (Labor Utilization Rate), workgroup productivity, and dominant factors that influence the masonry work in Griya Putri Tanjung Housing. The method used in the research was field observations for six houses by observing the effective work time, contribution work time, and ineffective work time, calculating the area of bricklaying and questionnaires to 12 workers. The questionnaires were processed with SPSS 24. The results obtained showed that the highest worker utility factor (LUR) was on day 2 of 88.89%. The Average LUR in Putri Tanjung Griya Housing is greater than 50%, so the work utility factor reaches the effective time. The highest average productivity of each workforce is on the 3rd day by a productivity value of 1.51 m2/hour/person. The most dominant factor was the time factor and implementation conditions (up to 82%), then the physical factor of labor (32,8%), managerial (-24,1%), the background of the employee (19,1%). The lowest factor was the group factor and the expertise of the workforce by a percentage of influence of -17,5%.
Keywords: housing, labor, bricklaying.
Article Details
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgment of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgment of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).
- This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
References
- Badan Pusat Statistik Nasional (BPS), 2012, laporan
- Djati, W.I., 2015. “Batu Bata Bolong Berkualitas” http://bandarlampungdanbisnis.blogspot.com/2015/06/batu-bata-bolong-berkualitas.html (diakses 9 Desember 2018).
- Hutasoit, J.P., Mochtar, S., dan Revo, L.I., 2017,“Analisis Produktivitas Tenaga Kerja Konstruksi pada Pekerjaan Pasangan Lantai Keramik dan Plasteran Dinding Menggunakan Metode Work Sampling”, Jurnal Sipil Statik, 5(4).
- Mandani, T., 2010, “Analisis Produktivitas Tenaga Kerja pada Pekerjaan Pasangan Bata”, Teknik Universitas Sebelas Maret, Surakarta.
- Maulidia, F., 2017, “Analisa Produktivitas dan Faktor yang mempengaruhi Kinerja Tukang pada Pemasangan Bata dengan Metode Productivity Rating”, Teknik Sipil Universitas Muhammadiyah Malang, Malang.
- Prayitno, B., Alfredo, S. F., dan Mahditia, P., 2012, “Kesejahteraan Rakyat atas Papan”, Kedeputian Bidang Koordinasi Perlindungan Sosial dan Perumahan Rakyat, Jakarta Pusat.
- Purwati, Y., 2005, “Analisis Produktivitas Tenaga Kerja pada Pekerjaan Plesteran Dinding dengan Metode Studi Gerak dan Waktu”, Teknik Sipil dan Perancangan Universitas Islam Indonesia,Yogyakarta.
- Rachman, A., dan Helmi, P., 2002, “Analisis Produktivitas Tukang Batu pada Pekerjaan Pasangan Bata”, Teknik Sipil dan PerencanaanUniversitas Islam Indonesia,Yogyakarta.
- Retno, D., dan Rustam., 2005, “Analisis Produktivitas Tenaga Kerja pada Pemasangan Bekisting Kolom Ditinjau dari Komposisi Kelompok Kerja”, Teknik Sipil dan Perancangan Universitas Islam Indonesia, Yogyakarta.
- Republik Indonesia., 2011, “Undang-Undang republic Indonesia Nomor 1 Tahun 2011 Tentang Perumahan dan Kawasan Permukiman”, Lembaran Negara RI Tahun 2011, Sekretariat Negara, Jakarta.
- Soeharto, I., 1995, “Manajemen Proyek dari Konseptual Sampai Operasional”, Erlangga, Jakarta.
- Tamamengka, J., Pingkan, A. K. P., dan Walangitan, D.R.O., 2016, “Analisis Tenaga Kerja Terhadap Produktivitas pada Proyek Konstruksi”, Tekno, 14(65).
- Tanto, D., Sri, M.D., dan Sugeng, P.B., 2012, “Faktor-Faktor yang Mempengaruhi Produktivitas Pekerjaan pada Pengerjaan Atap Baja Ringan di Perumahan Green Hills Malang”, Jurnal Rekayasa Sipil, 6(1).
References
Badan Pusat Statistik Nasional (BPS), 2012, laporan
Djati, W.I., 2015. “Batu Bata Bolong Berkualitas” http://bandarlampungdanbisnis.blogspot.com/2015/06/batu-bata-bolong-berkualitas.html (diakses 9 Desember 2018).
Hutasoit, J.P., Mochtar, S., dan Revo, L.I., 2017,“Analisis Produktivitas Tenaga Kerja Konstruksi pada Pekerjaan Pasangan Lantai Keramik dan Plasteran Dinding Menggunakan Metode Work Sampling”, Jurnal Sipil Statik, 5(4).
Mandani, T., 2010, “Analisis Produktivitas Tenaga Kerja pada Pekerjaan Pasangan Bata”, Teknik Universitas Sebelas Maret, Surakarta.
Maulidia, F., 2017, “Analisa Produktivitas dan Faktor yang mempengaruhi Kinerja Tukang pada Pemasangan Bata dengan Metode Productivity Rating”, Teknik Sipil Universitas Muhammadiyah Malang, Malang.
Prayitno, B., Alfredo, S. F., dan Mahditia, P., 2012, “Kesejahteraan Rakyat atas Papan”, Kedeputian Bidang Koordinasi Perlindungan Sosial dan Perumahan Rakyat, Jakarta Pusat.
Purwati, Y., 2005, “Analisis Produktivitas Tenaga Kerja pada Pekerjaan Plesteran Dinding dengan Metode Studi Gerak dan Waktu”, Teknik Sipil dan Perancangan Universitas Islam Indonesia,Yogyakarta.
Rachman, A., dan Helmi, P., 2002, “Analisis Produktivitas Tukang Batu pada Pekerjaan Pasangan Bata”, Teknik Sipil dan PerencanaanUniversitas Islam Indonesia,Yogyakarta.
Retno, D., dan Rustam., 2005, “Analisis Produktivitas Tenaga Kerja pada Pemasangan Bekisting Kolom Ditinjau dari Komposisi Kelompok Kerja”, Teknik Sipil dan Perancangan Universitas Islam Indonesia, Yogyakarta.
Republik Indonesia., 2011, “Undang-Undang republic Indonesia Nomor 1 Tahun 2011 Tentang Perumahan dan Kawasan Permukiman”, Lembaran Negara RI Tahun 2011, Sekretariat Negara, Jakarta.
Soeharto, I., 1995, “Manajemen Proyek dari Konseptual Sampai Operasional”, Erlangga, Jakarta.
Tamamengka, J., Pingkan, A. K. P., dan Walangitan, D.R.O., 2016, “Analisis Tenaga Kerja Terhadap Produktivitas pada Proyek Konstruksi”, Tekno, 14(65).
Tanto, D., Sri, M.D., dan Sugeng, P.B., 2012, “Faktor-Faktor yang Mempengaruhi Produktivitas Pekerjaan pada Pengerjaan Atap Baja Ringan di Perumahan Green Hills Malang”, Jurnal Rekayasa Sipil, 6(1).